Conversion of an existing not finalized hotel into an apartment building. The 6 levels (Basement, ground floor, mezzanine and 4 levels) reinforced concrete building was initially designed as a hotel. The proposed modifications are consisting in the addition of a composite slabs in some parts of the mezzanine, changing the facade sand modifications of the interior  partitions.
In order to facilitate the design phase and to minimize problems during construction, the structure was surveyed using 3D Laser Scanning.
The Design Phase of the project was started in February 2016 and it’s almost finalized, the project is waiting the approvals to enter the construction phase.

Project Details

CLIENT:Amitria Expert s.r.l.
PROGRESS:design phase
BUILT AREA:7478 sq. m.